ποΈ Site inspection at Savanna City Primary School.
The project is now 61% complete, with good progress across multiple work fronts, including brickwork, roofing, glazing, plastering, plumbing, electrical installations, stormwater infrastructure and perimeter fencing.
π§ Current activities also include door and burglar-proofing installations, screeding, sewer reticulation, attenuation tank backfilling, and ongoing roof structure works across several blocks, keeping the project on track.
β οΈ A key challenge remains as some subcontractors have not paid their employees, requiring urgent attention to avoid delays. The next phase will focus on progressing brickwork, roof structures, roof coverings and internal plastering to drive the project forward. π«
#TacklingG13 #GrowingGautengTogether